What joists does your deck need?
Measure the span from the house to the beam and pick your lumber. You'll get the smallest joist that carries it, and when you need a beam instead.
These joists carry it
2x10 at 16 in o.c.
2x10 is the smallest southern pine joist that spans 12 ft at 16 in. Or drop to 2x8 at 12 in.
- Span
- 12 ft12 ft
- Spacing
- 16 in o.c.
- Wood
- southern pine
- Joist
- 2x10
span = 12 ft = 144 in
2x6 at 16 in: max 108 in < 144 in
2x8 at 16 in: max 142 in < 144 in
2x10 at 16 in: max 168 in ≥ 144 in
2x12 at 16 in: max 198 in ≥ 144 in
design load = 40 psf live + 10 psf dead, IRC Table R507.6
Joists at 16 in on center
southern pine- 2x6 at 16 in o.c.Max span 9 ft. 12 in: 9 ft 11 in, 24 in: 7 ft 7 in3 ft short
- 2x8 at 16 in o.c.Max span 11 ft 10 in. 12 in: 13 ft 1 in, 24 in: 9 ft 8 in2 in short
- 2x10 at 16 in o.c.Max span 14 ft. 12 in: 16 ft 2 in, 24 in: 11 ft 5 inSmallest that works
- 2x12 at 16 in o.c.Max span 16 ft 6 in. 12 in: 18 ft, 24 in: 13 ft 6 inCarries it
No. 2 grade lumber, wet service. Spans from IRC 2021 Table R507.6.
If the joists run past the beam, keep the overhang to 1/4 of the back span. For 12 ft that's 3 ft. Put it in above and we'll recheck.
Span is the clear distance from the ledger or rim to the face of the beam. Not the deck depth.
These spans are for 40 psf. If your ground snow load is over 40 psf, your town will want the snow columns of the table.
Don't plan a hot tub on these numbers. A full tub runs 100 psf or more. That deck needs an engineer.
Hang each joist at the ledger in a galvanized or stainless joist hanger sized for the lumber. Fill every nail hole.
See 2x10 joist hangers on Amazon (opens Amazon in a new tab)As an Amazon Associate we earn from qualifying purchases.
How we work it out
We check your span against IRC Table R507.6, the deck joist table most towns enforce. It assumes No. 2 treated lumber, 40 psf of people and furniture, and 10 psf for the deck itself.
span in inches = feet × 12
passes when table max span ≥ your span
We start at 2x6 and go up until one carries the span at your spacing. If none do, we try tighter spacing. Past 18 ft, nothing in the table works. Add a beam in the middle and size each half.
If the joists run past the beam, the overhang can be 1/4 of the back span at most. Joists that overhang also get shorter allowed back spans, and we use those.
Where the numbers come from
More calculators
- MulchHow many yards of mulch for my beds?
- GravelHow many tons of gravel for my path or driveway?
- Topsoil and fillHow much soil to fill or level my yard?
- Sod and seedHow much sod or seed for my lawn?
- Paver patioHow many pavers and how much base for my patio?
- Retaining wallHow many blocks, and how tall before it needs an engineer?
- Concrete padHow much concrete for my shed or hot tub pad?
- FenceHow many posts, rails and pickets for my fence line?
- Shed fitWill a shed fit my setbacks and get through my gate?
- Hot tubCan my deck hold it, and can my panel power it?
- Sprinkler zonesHow many zones will my water pressure run?